Product Release Estimation
- Prioritize the product backlog.
- Ask your scrum team to select the best user stories to work on a single sprint.
- Example — 2+5+3+2+8 = 20 Story Points.
- Best case initial velocity = 20
- Worst case initial velocity = 20 x 30% = (20–6) = 14
- Calculating how many sprints
Best Case Sprints
Total story points/ Best Case Initial velocity =Total Sprints
140 (MVP1+MVP2)/ 20 =7 Sprints
Worst Case Sprints (with contingency)
Total story points/ Best Case Initial velocity =Total Sprints
140 (MVP1+MVP2)/ 14=10 Sprints
7. Calculating how many sprints for a release date
In another month (Assume today is 20/11/2022, so in another month means 20/12/2022),
Best Case Sprints
How many sprints to date x Best Case Initial Velocity = Total Story Points to date
4 x 20 = 80 Story Points
Worst Case Sprints
How many sprints to date x Best Case Initial Velocity = Total Story Points to date
4 x 14 = 56 Story Points
So to that date, we can deliver 56–80 Story Points
Gayathra Ranasinghe — Project Lead / Scrum Master
Certified Scrum Master(CSM), BEng(Hons),MBA,BTEC(AM),AMIESL,AMIMechE